Question 36

Which product identifies the management stages and timescales of a project?

  1. Project Brief
  2. Project Product Description
  3. Project Plan
  4. Initiation Stage Plan

Question 37

How should the Team Manager report that tolerances are forecast to be exceeded?

  1. Create an Exception Report
  2. Create a Highlight Report
  3. Raise an issue
  4. Grant a concession

Question 38

Which is a purpose of a Project Product Description?

  1. Records the costs and timescales for delivery of the project's final product
  2. Shows the dependencies between the project's products to aid planning
  3. Provides a list of all the products to be delivered by the project
  4. Defines what the project must deliver in order to gain acceptance

Question 39

Which is a purpose of a Product Description?

  1. Provide the cost tolerance available for individual products
  2. Define reporting frequency
  3. Record the quality checks completed for the End Stage Report
  4. Document the level of quality required of a product

Question 40

Which is a purpose of the Business Case theme?

  1. Identify which role is responsible for producing the Business Case
  2. Identify the project's outputs
  3. Establish the controls to manage changes that may impact the project benefits
  4. Establish a viable investment proposition