Question 36
Which product identifies the management stages and timescales of a project?
- Project Brief
- Project Product Description
- Project Plan
- Initiation Stage Plan
Question 37
How should the Team Manager report that tolerances are forecast to be exceeded?
- Create an Exception Report
- Create a Highlight Report
- Raise an issue
- Grant a concession
Question 38
Which is a purpose of a Project Product Description?
- Records the costs and timescales for delivery of the project's final product
- Shows the dependencies between the project's products to aid planning
- Provides a list of all the products to be delivered by the project
- Defines what the project must deliver in order to gain acceptance
Question 39
Which is a purpose of a Product Description?
- Provide the cost tolerance available for individual products
- Define reporting frequency
- Record the quality checks completed for the End Stage Report
- Document the level of quality required of a product
Question 40
Which is a purpose of the Business Case theme?
- Identify which role is responsible for producing the Business Case
- Identify the project's outputs
- Establish the controls to manage changes that may impact the project benefits
- Establish a viable investment proposition