Question 31
Which statement is FALSE?
A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
A project's output is any of the project's specialist products
A project benefit is only realized after the project has closed
A project outcome is the result of the change derived from using the project's outputs
Question 32
Which is a responsibility of the managing level within the project management team?
Set project tolerances
Approve stage completion
Ensure that the products are produced within the constraints agreed with the Project Board
Appoint the project management team
Question 33
Which of the following statements about stakeholders are true? 1. Someone who thinks they will be affected by a project is a stakeholder on that project 2. Stakeholders may be internal or external to the corporate organization
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true
Question 34
Which is a purpose of quality planning?
Define the structure of the project management team
Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
Document approval records for those project products that have met their quality criteria
Produce the Project Plan with resource and schedule information
Question 35
Identify the missing word in the following sentence. The purpose of the [?] theme is to identify, assess and control uncertainty.