Question 46

Which of the following statements about customer's quality expectations and acceptance criteria are true? 1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements. 2. Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 are true

Question 47

Which statement about stages is true?

  1. Management stages should be of the same duration
  2. The use of technical stages is mandatory
  3. The use of management stages is mandatory
  4. Management stages are driven by specialist teams

Question 48

Who should act as the communication channel between a project and corporate or programme management?

  1. Project Board
  2. Project Assurance
  3. Project Manager
  4. Project Support