Question 41

Who is the key project decision-maker in the project management team?

  1. Corporate management
  2. Executive
  3. Change Authority
  4. Project Manager

Question 42

Which is a purpose of a Project Brief?

  1. Capture lessons from previous projects
  2. Ensure that there is a common understanding of the starting point for the project
  3. Confirm that the Project Plan is able to deliver the Business Case
  4. Define the quality techniques and standards to be applied during the project

Question 43

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

  1. Specify the desired result
  2. Provide the resources and skills to deliver the desired result
  3. Pay for the project
  4. Specify the benefits of the project

Question 44

Which describes risk impact?

  1. Timeframe within which the risk might occur
  2. The trigger that occurred giving rise to the risk
  3. The effect of the risk on the delivery of project objectives
  4. How likely the risk is to occur in a given project situation

Question 45

Which is a purpose of the Controlling a Stage process?

  1. Produce a Team Plan for the work to be assigned to a Team Manager
  2. Select and implement actions that will resolve deviations from a plan within tolerance
  3. Obtain approvals for products delivered in a Work Package