Question 1

When considering risks, which describes an opportunity in a project?

  1. An uncertain event that could have a negative impact on objectives
  2. An uncertain event that could have a favourable impact on objectives
  3. An event that has occurred resulting in a negative impact on objectives
  4. An event that has occurred resulting in a favourable impact on objectives

Question 2

How many tasks does the product-based planning technique describe?

  1. One
  2. Two
  3. Three
  4. Four

Question 3

Which is an objective of the quality review technique?

  1. To identify a product's quality criteria
  2. To provide assurance that the project is being conducted properly
  3. To assess that a product conforms to set criteria
  4. To ensure that staff are properly trained in the quality methods

Question 4

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

  1. Risk category
  2. Risk description
  3. Risk response
  4. Risk status

Question 5

If an informal issue is defined as a problem or concern, where should it first be recorded?

  1. Issue Register
  2. Risk Register
  3. Daily Log
  4. Exception Report