PRF practice questions, page 2 of 10, with answer review and explanations.
Question 6
Which of the following statements about the Project Initiation Documentation are true? 1. The Project Initiation Documentation is used to ensure that a sound basis exists. 2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project before the Project Board authorizes a project,
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true
Question 7
Which is the purpose of the Change theme?
Prevent change to baselined products
Identify, assess and control any potential and approved changes to baselined products
Establish mechanisms to monitor and compare actual achievements against those planned
Assess and control uncertainty
Question 8
Why is a Project Brief produced?
To act as a trigger for the Starting up a Project process
To record the strategies and management controls to be used by a project
To provide a full and firm foundation for the initiation of a project
To be used by the Project Board as a basis for reviewing the progress of a project
Question 9
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
the measurement of benefits NOT yet realized
the handover of products
open issues and risks
the release of resources
Question 10
In what process is the authorization to deliver the project's products given?