Question 11

Which of the following is NOT part of quality planning?

  1. Define quality responsibilities
  2. Gain acceptance of the project product
  3. Agree acceptance criteria
  4. Set quality tolerances

Question 12

Which should be provided by a project mandate?

  1. Terms of reference
  2. Detailed Business Case
  3. Stage tolerances
  4. Initiation Stage Plan

Question 13

Which is an objective of the Starting up a Project process?

  1. Identify who will be responsible for creating the Project Plan
  2. Agree how the project will be monitored and controlled after initiation
  3. Authorize the Project Manager to proceed with the initiation stage
  4. Agree how issues and changes will be identified, assessed and controlled

Question 14

Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,

  1. Management strategies
  2. Plan
  3. Stakeholder interests
  4. Time-driven controls

Question 15

If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

  1. Senior User
  2. Executive
  3. Corporate/programme management
  4. Senior Supplier