PRF

PRF practice questions, page 4 of 10, with answer review and explanations.

Question 16

Which is a purpose of the Risk theme?

  1. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
  2. Establish a cost-effective procedure to identify, assess and control uncertainty
  3. Establish mechanisms to control any unacceptable deviations from plan
  4. Establish mechanisms to manage risks at the corporate or programme level of an organization

Question 17

Which is part of the PRINCE2 definition of a project?

  1. An undertaking that consists of at least two management stages
  2. A description of what must be delivered in order to gain acceptance
  3. The total of a plan's products
  4. A temporary organization that is created for the purpose of delivering business products

Question 18

Which is a type of issue?

  1. A lesson
  2. A request for change
  3. An Exception Report
  4. A risk with an estimated high impact

Question 19

Identify the missing words in the following sentence: The six aspects of project performance to be managed are [?] costs, timescales and scope.

  1. benefits, progress, risk,
  2. benefits, quality, risk,
  3. change, quality, progress,
  4. benefits, customers, quality,

Question 20

Which task is performed by the Change Authority?

  1. Set a change budget
  2. Approve or reject a request for change within approved limits
  3. Refer changes that exceed budgetary limits to the Project Manager for approval
  4. Update the configuration management system when a change is approved