Question 16
Which is a purpose of the Risk theme?
- Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
- Establish a cost-effective procedure to identify, assess and control uncertainty
- Establish mechanisms to control any unacceptable deviations from plan
- Establish mechanisms to manage risks at the corporate or programme level of an organization
Question 17
Which is part of the PRINCE2 definition of a project?
- An undertaking that consists of at least two management stages
- A description of what must be delivered in order to gain acceptance
- The total of a plan's products
- A temporary organization that is created for the purpose of delivering business products
Question 18
Which is a type of issue?
- A lesson
- A request for change
- An Exception Report
- A risk with an estimated high impact
Question 19
Identify the missing words in the following sentence: The six aspects of project performance to be managed are [?] costs, timescales and scope.
- benefits, progress, risk,
- benefits, quality, risk,
- change, quality, progress,
- benefits, customers, quality,
Question 20
Which task is performed by the Change Authority?
- Set a change budget
- Approve or reject a request for change within approved limits
- Refer changes that exceed budgetary limits to the Project Manager for approval
- Update the configuration management system when a change is approved