Question 21
Identify the missing word in the following sentence: A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.
costs
risks
benefits
issues
Question 22
Which process provides the Project Board with the information it requires in order to commit resources to the project?
Managing Product Delivery
Initiating a Project
Controlling a Stage
Directing a Project
Question 23
Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?
Principles
Processes
Tailoring PRINCE2 to the project environment
Themes
Question 24
Which should be funded by a change budget?
Increase in agreed scope
Initiation stage
Change Authority
Handover activities
Question 25
Which of the following describes a use of a Configuration Item Record?
Define the identification scheme to be applied to the project
Identify the techniques and procedures required within the Work Package
Record the change in a product's status
Record the reporting requirements for the Work Package