Question 21

Identify the missing word in the following sentence: A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.

  1. costs
  2. risks
  3. benefits
  4. issues

Question 22

Which process provides the Project Board with the information it requires in order to commit resources to the project?

  1. Managing Product Delivery
  2. Initiating a Project
  3. Controlling a Stage
  4. Directing a Project

Question 23

Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

  1. Principles
  2. Processes
  3. Tailoring PRINCE2 to the project environment
  4. Themes

Question 24

Which should be funded by a change budget?

  1. Increase in agreed scope
  2. Initiation stage
  3. Change Authority
  4. Handover activities

Question 25

Which of the following describes a use of a Configuration Item Record?

  1. Define the identification scheme to be applied to the project
  2. Identify the techniques and procedures required within the Work Package
  3. Record the change in a product's status
  4. Record the reporting requirements for the Work Package