Question 26

Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

  1. Principles
  2. Processes
  3. Tailoring PRINCE2 to the project environment
  4. Themes

Question 27

Which should be funded by a change budget?

  1. Increase in agreed scope
  2. Initiation stage
  3. Change Authority
  4. Handover activities

Question 28

Which of the following describes a use of a Configuration Item Record?

  1. Define the identification scheme to be applied to the project
  2. Identify the techniques and procedures required within the Work Package
  3. Record the change in a product's status
  4. Record the reporting requirements for the Work Package

Question 29

Which characteristic distinguishes a project from regular business operations?

  1. Produces benefits
  2. Introduces business change
  3. Manages stakeholders
  4. Incurs cost

Question 30

What process aims to ensure accurate progress information is provided to the Project Manager?

  1. Starting up a Project
  2. Managing a Stage Boundary
  3. Managing Product Delivery
  4. Directing a Project