Question 26
Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?
- Principles
- Processes
- Tailoring PRINCE2 to the project environment
- Themes
Question 27
Which should be funded by a change budget?
- Increase in agreed scope
- Initiation stage
- Change Authority
- Handover activities
Question 28
Which of the following describes a use of a Configuration Item Record?
- Define the identification scheme to be applied to the project
- Identify the techniques and procedures required within the Work Package
- Record the change in a product's status
- Record the reporting requirements for the Work Package
Question 29
Which characteristic distinguishes a project from regular business operations?
- Produces benefits
- Introduces business change
- Manages stakeholders
- Incurs cost
Question 30
What process aims to ensure accurate progress information is provided to the Project Manager?
- Starting up a Project
- Managing a Stage Boundary
- Managing Product Delivery
- Directing a Project