Question 21
Which is a type of issue?
A lesson
A request for change
An Exception Report
A risk with an estimated high impact
Question 22
Identify the missing words in the following sentence: The six aspects of project performance to be managed are [?] costs, timescales and scope,
benefits, progress, risk,
benefits, quality, risk,
change, quality, progress,
benefits, customers, quality,
Question 23
Which task is performed by the Change Authority?
Set a change budget
Approve or reject a request for change within approved limits
Refer changes that exceed budgetary limits to the Project Manager for approval
Update the configuration management system when a change is approved
Question 24
Identify the missing word in the following sentence: A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.
costs
risks
benefits
issues
Question 25
Which process provides the Project Board with the information it requires in order to commit resources to the project?