Question 16
Which is an objective of the Starting up a Project process?
Identify who will be responsible for creating the Project Plan
Agree how the project will be monitored and controlled after initiation
Authorize the Project Manager to proceed with the initiation stage
Agree how issues and changes will be identified, assessed and controlled
Question 17
Identify the missing word(s) in the following sentence: PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
Management strategies
Plan
Stakeholder interests
Time-driven controls
Question 18
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
Senior User
Executive
Corporate/program management
Senior Supplier
Question 19
Which is a purpose of the Risk theme?
Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
Establish a cost-effective procedure to identify, assess and control uncertainty
Establish mechanisms to control any unacceptable deviations from plan
Establish mechanisms to manage risks at the corporate or programme level of an organization
Question 20
Which is part of the PRINCE2 definition of a project?
An undertaking that consists of at least two management stages
A description of what must be delivered in order to gain acceptance
The total of a plan's products
A temporary organization that is created for the purpose of delivering business products