Question 46

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

  1. Specify the desired result
  2. Provide the resources and skills to deliver the desired result
  3. Pay for the project
  4. Specify the benefits of the project

Question 47

Which describes risk impact?

  1. Timeframe within which the risk might occur
  2. The trigger that occurred giving rise to the risk
  3. The effect of the risk on the delivery of project objectives
  4. How likely the risk is to occur in a given project situation

Question 48

Which is a purpose of the Controlling a Stage process?

  1. Produce a Team Plan for the work to be assigned to a Team Manager
  2. Select and implement actions that will resolve deviations from a plan within tolerance
  3. Obtain approvals for products delivered in a Work Package
  4. Update a Project Plan to incorporate the actuals from a Stage Plan