Question 46
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
- Specify the desired result
- Provide the resources and skills to deliver the desired result
- Pay for the project
- Specify the benefits of the project
Question 47
Which describes risk impact?
- Timeframe within which the risk might occur
- The trigger that occurred giving rise to the risk
- The effect of the risk on the delivery of project objectives
- How likely the risk is to occur in a given project situation
Question 48
Which is a purpose of the Controlling a Stage process?
- Produce a Team Plan for the work to be assigned to a Team Manager
- Select and implement actions that will resolve deviations from a plan within tolerance
- Obtain approvals for products delivered in a Work Package
- Update a Project Plan to incorporate the actuals from a Stage Plan