Question 31

Where should an off-specification be recorded?

  1. Risk Register
  2. Issue Register
  3. Work Package
  4. Configuration Management Strategy

Question 32

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin?

  1. End Stage Report
  2. Team Plan
  3. Work Package
  4. Project Plan

Question 33

Which is a benefit of using PRINCE2?

  1. Provides a defined structure of accountability, delegation, authority and communication
  2. Includes techniques for critical path analysis and earned value analysis
  3. Enables a Project Manager to be accountable for the success of a project
  4. Prevents any changes once the scope of a project has been agreed

Question 34

Which statement is FALSE?

  1. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
  2. A project's output is any of the project's specialist products
  3. A project benefit is only realized after the project has closed
  4. A project outcome is the result of the change derived from using the project's outputs

Question 35

Which is a responsibility of the managing level within the project management team?

  1. Set project tolerances
  2. Approve stage completion
  3. Ensure that the products are produced within the constraints agreed with the Project Board
  4. Appoint the project management team