Question 6
Which is a purpose or the ‘initiating a project’ process?
To prepare the contract for the project to enable the project board to commit to delivery
To provide the project board with just enough information to decide whether to approve the initiation stage
To provide the opportunity for the senior user to confirm (hat they find the project product acceptable
To enable the project board to empower the project manager to work within delegated authority limits
Question 7
According to the ‘exception management’ technique, when should the team manager raise an issue?
When the team manager predicts that a product will cause a stage to exceed its time tolerance
When the team manager identifies that a product is going to be delivered late
When the team manager predicts that a product will cause a work package to exceed its time tolerance
When the team manager identities that the work package has already exceeded its time tolerance
Question 8
The project manager has created a list or tasks to produce the project’s products. Which step of the ‘organizational design and development’ technique should be informed by this list?
Design the project ecosystem
Understand the organizational ecosystem
Manage the ongoing changes to the project ecosystem
Develop the project ecosystem
Question 9
When developing a business case, the project manager reviewed the end project report from a previous similar project that stated that costs had been underestimated on the project. Which principle is being applied by the project manager when reviewing this information?
Learn from experience
Tailor to suit the project
Manage by stages
Ensure continued business justification
Question 10
Which is a purpose of the plans practice?
To enable an event that requires project management actions to be controlled
To provide the standards against which the project products can be quality controlled
To provide the basis for control against which a project’s progress can be monitored
To enable control of opportunities and threats, that could impact on delivery of the business objectives