Question 1
Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?
- Increase the frequency of checkpoint reports
- Allow the team manager more flexibility to exceed cost tolerance
- Increase the frequency of event-driven controls
- Increase the frequency of escalations by the team manager
Question 2
Which action contributes to achieving the ‘ensure continued business justification’ principle?
- Adapting PRINCE2 Project Management to the scale and complexity of the project
- Assigning roles and responsibilities for the project team
- Establishing limits of authority on the project based on defined tolerances
- Ensuring that the project remains worthwhile throughout the lifecycle of the project
Question 3
Which term is defined as the means by which an organization transitions from its current state to the target state?
- Progress management
- Change control
- Change management
- Risk management
Question 4
Which is a purpose of the communication management approach?
- To describe the processes used to engage with stakeholders in identifying uncertainties
- To describe the techniques required to make the project product acceptable to stakeholders
- To describe the target organizational state and how the business will move to that new state
- To define how the project team intends to obtain responses from stakeholders
Question 5
The project board needs to confirm that there is enough information to initiate the project. What should the project beard review?
- Project initiation documentation
- Project brief
- Benefits management approach
- Project plan