Question 21

Which term is defined as a product that will not meet its quality specifications?

  1. Concern
  2. Request for change
  3. Off-specification
  4. Problem

Question 22

Why is change management important in a project?

  1. It provides processes and management products to use when requesting a change
  2. It provides clarity on how the culture of an organization needs to adapt over time
  3. It provides confidence that the project can meet its objectives and has continued business justification
  4. It provides a controlled and bidirectional flow of information to key influencers

Question 23

Which control is time-driven?

  1. The creation of an exception report
  2. The completion of the PID
  3. The creation of a highlight report
  4. The end of the financial year

Question 24

The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?

  1. Risk management approach
  2. Issue report
  3. Issue management approach
  4. Issue register