Question 21
Which term is defined as a product that will not meet its quality specifications?
Concern
Request for change
Off-specification
Problem
Question 22
Why is change management important in a project?
It provides processes and management products to use when requesting a change
It provides clarity on how the culture of an organization needs to adapt over time
It provides confidence that the project can meet its objectives and has continued business justification
It provides a controlled and bidirectional flow of information to key influencers
Question 23
Which control is time-driven?
The creation of an exception report
The completion of the PID
The creation of a highlight report
The end of the financial year
Question 24
The project manager needs to know what modifications have been proposed to an approved product during the stage. Which management product should the project manager review?