PgMP Practice Test

PgMP Practice Test practice questions, page 25 of 29, with answer review and explanations.

Question 121

You are the program manager for a construction program. In this program you are requiring that all workers adhere to the identified safety requirements. Some of the work in the program you've decided is too risky for the program team members so you've hired specialists to manage the dangerous work. The outsourcing of the dangerous work to a specialist is what type of risk response?

  1. Avoidance
  2. Mitigation
  3. Transference
  4. Enhancing

Question 122

You are the program manager for your organization and management has asked you to be certain to finalize the lessons learned documentation for your program. When will the lessons learned documentation be created?

  1. Lessons learned are in program execution.
  2. Lessons learned are created at each program deliverable.
  3. Lessons learned are created during the program closure.
  4. Lessons learned are created during the program archive.

Question 123

You are the program manager for the HQM Program. Your program has sixteen constituent projects around the world. You are requiring that each project manager and project management team use the same forms, software, and templates to create standardization in each project. What term is assigned to the forms, templates, and software that your program will provide for your projects?

  1. Program governance
  2. Project management assets
  3. Enterprise environmental factors
  4. Organizational process assets

Question 124

You are the program manager of a new program in your organization. This program will last for one year and your program team will work full-time on the effort. The nature of the work requires that the program team work closely together for the next year, but many of the program team members have never met one another. You decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?

  1. Cost of quality
  2. Storming
  3. Forming
  4. Team development

Question 125

A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?

  1. Defect repair validation
  2. Lesson learned documentation
  3. Corrective actions
  4. Preventive actions