Review 713 PGMP practice questions with answer explanations and community insights.
Question 1
Your program has 121 stakeholders that you'll need to communicate with. Your communications management plan defines how the communication should happen, what should be communicated, and the expected modality of the communications. You'll also need which one of the following as an input to the information distribution process in your program?
Change requests
Earned value management results
Stakeholder analysis plan
Performance reports
Question 2
What is the formula to determine earned value (EV) for a program?
Percent complete times percent remaining in the program
Percent completes time the program cost estimate
Percent complete times the program budget at completion
Percent complete times the program cost of labor and materials
Question 3
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?
Screening system
Scoring model
Vendor analysis requirements
Evaluation criteria
Question 4
You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns, perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?
Requirements document
Project charter
Business case
Scope statement
Question 5
You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you completing to ensure that the work is done accordingly to scope?