Question 116
Which of the following types of floats are available? Each correct answer represents a complete solution. Choose two.
Half float
Full float
Total float
Free float
Question 117
You are the program manager of the YHT Program. You have been working with a vendor in the program but have decided that the contract between your program and the vendor needs to be terminated. What two things must be documented if you wish to terminate a vendor's contract?
Contract and the quality measurements for the vendor's work
The scope verification document and the termination notice
Contract and scope verification process documents
Work that has been completed and uncompleted work
Question 118
In your program you must adhere to Six Sigma as part of your organization's enterprise environmental factors. There is terminology, reports, and measurements that you are expected to use as part of your program. Six Sigma is an example of what program management process?
Quality control
Process improvement
Scope verification
Quality assurance
Question 119
You are the program manager of the NHQ Program. You will need to initiate six projects for your program. When should project initiating happen within a program?
Whenever the program needs to initiate projects, it may, as long as the program has not entered the closing processes of the program.
With program execution
With program initiation
With program planning
Question 120
Joan is the program manager for her organization. Throughout the program life cycle there will be several elements, resources, and benefits that can be transitioned from her program to the organization. What document defines how these things can be transferred from the program to the organization?