PgMP Practice Test practice questions, page 23 of 29, with answer review and explanations.
Question 111
Which project management meeting allows stakeholders to meet one another and to learn about the project?
Project scope review
Project authorization meeting
Project status meeting
Project kick-off meeting
Question 112
You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?
Life cycle costing estimates
Lessons learned documentation
Operational transfer plan
Program closure reports
Question 113
Ned is the program manager for his organization and he's considering some new materials for his program. He and his team have never worked with these materials before and he wants to ask the vendor for some additional information, a demon, and even some samples. What type of a document should Ned send to the vendor?
RFI
RFP
RFQ
IFB
Question 114
If a program has a budget of completion of $550,000, is 25 percent complete, and has spent $135,000 what is the cost variance (CV)?
.99
-$2,500
$2,500
1.02
Question 115
Which benefit measurement method considers the value of each time period's return for a project that will create deliverables over multiple time periods?