Question 16

If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

  1. Senior User
  2. Executive
  3. Corporate/programme management
  4. Senior Supplier

Question 17

Which is a purpose of the Risk theme?

  1. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
  2. Establish a cost-effective procedure to identify, assess and control uncertainty
  3. Establish mechanisms to control any unacceptable deviations from plan
  4. Establish mechanisms to manage risks at the corporate or programme level of an organization

Question 18

Which is part of the PRINCE2 definition of a project?

  1. An undertaking that consists of at least two management stages
  2. A description of what must be delivered in order to gain acceptance
  3. The total of a plan's products
  4. A temporary organization that is created for the purpose of delivering business products

Question 19

Which is a type of issue?

  1. A lesson
  2. A request for change
  3. An Exception Report
  4. A risk with an estimated high impact

Question 20

Identify the missing words in the following sentence, The six aspects of project performance to be managed are [?] costs, timescales and scope,

  1. benefits, progress, risk,
  2. benefits, quality, risk,
  3. change, quality, progress,
  4. benefits, customers, quality,