Review 142 EX0-002 practice questions with answer explanations and community insights.
Question 1
When considering risks, which describes an opportunity in a project?
An uncertain event that could have a negative impact on objectives
An uncertain event that could have a favourable impact on objectives
An event that has occurred resulting in a negative impact on objectives
An event that has occurred resulting in a favourable impact on objectives
Question 2
Which of the following statements about lines of authority and reporting are true? 1, The Project Manager has day-to-day control for a management stage within the limits laid, 2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true
Question 3
How many tasks does the product-based planning technique describe?
One
Two
Three
Four
Question 4
Which is an objective of the quality review technique?
To identify a product's quality criteria
To provide assurance that the project is being conducted properly
To assess that a product conforms to set criteria
To ensure that staff are properly trained in the quality methods
Question 5
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?
Risk category
Risk description
Risk response
Risk status
We are moving to a new platform
CertificationTest is being migrated. Some pages may be slow or briefly unavailable; everything will be back to normal within a few hours. If you run into any issue, email support@certificationtest.net.