Question 21

Which task is performed by the Change Authority?

  1. Set a change budget
  2. Approve or reject a request for change within approved limits
  3. Refer changes that exceed budgetary limits to the Project Manager for approval
  4. Update the configuration management system when a change is approved

Question 22

Identify the missing word in the following sentence, A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.

  1. costs
  2. risks
  3. benefits
  4. issues

Question 23

Which process provides the Project Board with the information it requires in order to commit resources to the project?

  1. Managing Product Delivery
  2. Initiating a Project
  3. Controlling a Stage
  4. Directing a Project

Question 24

Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?

  1. Principles
  2. Processes
  3. Tailoring PRINCE2 to the project environment
  4. Themes

Question 25

Which should be funded by a change budget?

  1. Increase in agreed scope
  2. Initiation stage
  3. Change Authority
  4. Handover activities