Question 11
In what process is the authorization to deliver the project's products given?
Starting up a Project
Initiating a Project
Managing a Stage Boundary
Directing a Project
Question 12
Which of the following is NOT part of quality planning?
Define quality responsibilities
Gain acceptance of the project product
Agree acceptance criteria
Set quality tolerances
Question 13
Which should be provided by a project mandate?
Terms of reference
Detailed Business Case
Stage tolerances
Initiation Stage Plan
Question 14
Which is an objective of the Starting up a Project process?
Identify who will be responsible for creating the Project Plan
Agree how the project will be monitored and controlled after initiation
Authorize the Project Manager to proceed with the initiation stage
Agree how issues and changes will be identified, assessed and controlled
Question 15
Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,