Question 11

In what process is the authorization to deliver the project's products given?

  1. Starting up a Project
  2. Initiating a Project
  3. Managing a Stage Boundary
  4. Directing a Project

Question 12

Which of the following is NOT part of quality planning?

  1. Define quality responsibilities
  2. Gain acceptance of the project product
  3. Agree acceptance criteria
  4. Set quality tolerances

Question 13

Which should be provided by a project mandate?

  1. Terms of reference
  2. Detailed Business Case
  3. Stage tolerances
  4. Initiation Stage Plan

Question 14

Which is an objective of the Starting up a Project process?

  1. Identify who will be responsible for creating the Project Plan
  2. Agree how the project will be monitored and controlled after initiation
  3. Authorize the Project Manager to proceed with the initiation stage
  4. Agree how issues and changes will be identified, assessed and controlled

Question 15

Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,

  1. Management strategies
  2. Plan
  3. Stakeholder interests
  4. Time-driven controls