Question 31
In what table are Change records stored?
Change [change_task]
Change Request [rfc]
Change Request [change_request]
Change [change]
Change [task_change]
Question 32
Risk is configured by default, to calculate Risk = High for a change that is scheduled with only 3 days lead time. Your customer’s change policy requires that changes be requested with 5 days lead time. How would you satisfy this requirement?
Update the Risk Property for Insufficient lead time
Update the Risk Assessment Matrix for Insufficient lead time
Update the Calculate Risk UI Action
Update the Risk Matrix for insufficient lead time
Update the Risk Condition for Insufficient lead time
Question 33
How are Releases related to Projects?
Project tasks and Release tasks are interchangeable
Projects can be part of one or more releases
Project features are components of a release
Projects need to be completed before releases can be defined
Projects are used to do root cause analysis for releases
Question 34
What baseline Change Flows support the baseline Normal Change model?
Change - Normal - Assess, Change - Normal - Authorize, Change - Normal - Implement Change - Implementation tasks
Change - Normal - New, Change - Normal - Review, Change - Normal - Close, Change - Implementation tasks
Change - Normal - New, Change - Normal - Assess, Change - Normal - Implement, Change - Implementation tasks
Change - Normal - Assess, Change - Normal - Authorize, Change - Normal - Close, Change - Implementation tasks
Question 35
Which of the following Change Task Types are available by default? (Choose three.)