Question 41

Which of the following lists represents the outputs of the Monitor Communications process?

  1. Project communications, project management plan updates, project documents updates, and organizational process assets updates
  2. Work performance information, change requests, project management plan updates, and project documents updates
  3. Communications management plan, project management plan updates, work performance report, and project documents update
  4. Stakeholder engagement plan, change requests, project management plan updates, and project documents updates

Question 42

A project team member is estimating the cost of an activity and is checking documentation from previous similar projects. Which estimation method is the project manager using to complete this task?

  1. Bottom-up estimating
  2. Three-point estimating
  3. Analogous estimating
  4. Parametric estimating

Question 43

Which are inputs for the Plan Quality Management process?

  1. Quality metrics, project documents, and financial performance
  2. Quality management plan, project documents, and quality metrics
  3. Project management plan, project documents, and organizational process assets
  4. Project management plan, quality metrics, and project documents

Question 44

What should the project manager use to evaluate the politics and power structure among stakeholders inside and outside of the organization?

  1. Expert judgment
  2. Interpersonal skills
  3. Team agreements
  4. Communication skills

Question 45

The project manager has the following information about the estimated duration for an activity: ✑ Most likely [tM] `" 15 days ✑ Pessimistic [tP] `" 20 days ✑ Optimistic [tO] `" 10 days What is the estimated duration of this activity, according to the triangular distribution technique?

  1. 10 days
  2. 15 days
  3. 12.5 days
  4. 5 days