Question 46
Which is a major component of an agreement?
- Change request handling
- Risk register templates
- Lessons learned register
- Procurement management plan
Question 47
Which statement is related to the project manager's sphere of influence at the organizational level?
- A project manager interacts with other project managers to detect common interests and impacts their projects.
- A project manager facilitates communication between the suppliers and contractors on the project.
- A project manager considers the current industry trends and evaluates how they can impact or be applied to the project.
- A project manager may inform other professionals about the value of project management.
Question 48
What process group establishes project scope, refines objectives, and defines the actions necessary to attain project objectives?
- Executing
- Planning
- Initiating
- Monitoring and Controlling
Question 49
Which are examples of processes that may be used once or at predefined points in the project life cycle?
- Develop Project Charter and Close Project or Phase
- Define Activities and Acquire Resources
- Control Schedule and Conduct Procurements
- Monitor Communications and Control Costs
Question 50
After defining activities in project schedule management, which processes should a project manager follow?
- Sequence Activities and Estimate Activity Durations
- Estimate Activity Durations and Control Schedule
- Develop Schedule and Control Schedule
- Review Activities and Develop Schedule