CAPM Practice Test

CAPM Practice Test practice questions, page 11 of 21, with answer review and explanations.

Question 51

Which of the following tasks is related to the Perform Qualitative Risk Analysis process?

  1. Identify the project risks and assign a probability of occurrence
  2. Perform a sensitivity analysis to determine which risk has the most potential for impacting the project
  3. Analyze the effect of identified project risks as numerical data
  4. Prioritize each protect risk and assign the probability of occurrence and impact for each one

Question 52

The project manager needs to manage a critical issue immediately, and this requires action from the upper management of a specific stakeholder group. Which plan should the project manager consult?

  1. Risk management plan
  2. Communications management plan
  3. Change management plan
  4. Stakeholder engagement plan

Question 53

During what project management process does the project team begin identifying risks?

  1. Initiating
  2. Planning
  3. Executing
  4. Monitoring and Controlling

Question 54

A project manager is reviewing the change requests for project documents, deliverables, and the project plan. In which project management process does this review belong?

  1. Monitor and Control Project Work
  2. Direct and Manage Project Work
  3. Close Project or Phase
  4. Perform Integrated Change Control

Question 55

Which format can a network diagram take?

  1. Flow chart
  2. Control chart
  3. Affinity diagram
  4. Cause-and-effect diagram