Question 101

Select two key benefits of the Control Procurements process. (Choose two.)

  1. Enables the development of make-or-buy decisions
  2. Ensures that contract performance meets the terms of the legal agreement
  3. Guarantees that legal agreements influence vendor selection
  4. Assures that legal agreements guide contract closings
  5. Helps determine whether a certain type of contract should be used

Question 102

A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?

  1. The project manager should identify and deal with stakeholders only during the execution phase.
  2. Stakeholder satisfaction should be identified immediately and managed as a project objective.
  3. The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
  4. Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.

Question 103

Which of the following set of elements is part of an effective communications management plan?

  1. Escalation processes, person responsible for communicating the information, glossary of common terminology, methods or technologies used to convey the information
  2. Phone book directory, stakeholder communication requirements, project charter, glossary of common terminology
  3. Organizational chart, escalation processes, person responsible for communicating the information, project management plan, glossary of common terminology
  4. Glossary of common terminology, constraints derived from specific legislation and regulation, person responsible for communicating information, project management plan, resource management plan