Question 96
What internal enterprise environmental factor (EEF) can impact a project?
Cultural influences
Physical environmental elements
Commercial databases
Infrastructure
Question 97
A protect manager needs to request outside support for a statement of work (SOW) that is not precise. Which kind of contract does the project manager need to create?
Time and material (T&M)
Cost plus fixed fee (CPFF)
Fixed price
Cost plus award fee (CPAF)
Question 98
Which is a list of organizational systems that may have an impact on a project?
Internal policies, company procedures, and organizational resources
Company culture, purchasing system, and project management information system
Organizational structure, governance framework, and management elements
Organizational process assets, enterprise environmental factors, and corporate knowledge
Question 99
Which set of activities should a project manager use as part of the Develop Team process?
Training and establishing ground rules
Networking activities and estimating team resources
Conflict management activities and tracking team performance
Recruit new team members and training
Question 100
Which set of competencies should a project manager have?
Leadership, strategic and business management, and technical project management
Expertise in the industry, leadership and business management, and bilingual skills
Technical project management, expertise in every rote, and PMP certification
Expertise in every detail on project activities, PMP certification, and leadership