Question 91
The project manager is working with some functional managers and stakeholders on the resource management plan. Which elements may be included in this plan?
Team values, team agreements, and conflict resolution process
Conflict resolution process, communication guidelines, and meeting schedules
Team roles and responsibilities, team management, and training plan
Resource requirements, resource assignments, and team performance assessments
Question 92
A new project manager wishes to recommend creating a project management office to senior management. Which statement would the project manager use to describe the importance of creating the project management office?
It will give the project manager independence to make decisions without other departmental input.
It integrates organizational data and information to ensure that strategic objectives are fulfilled.
The project management office can execute administrative tasks.
The project management office can coordinate projects.
Question 93
In order to detect quality issues earlier in the project life cycle, the project manager is using an agile/adaptive environment. What is the main difference between waterfall and agile/adaptive development approaches for Project Quality Management?
The frequency of the quality and review steps
The number of deliverables
The duration of each of the quality and review steps
The tools used in the quality and review steps
Question 94
An important project stakeholder has low risk tolerance. Which type of communication should a project manager use to provide this stakeholder with a difficult update?
Informal conversation
Face-to-face meeting
Short email update
Written report
Question 95
Which tools and techniques should a project manager use to monitor risks?
Expert judgment, data analysis, and interpersonal and team skills