CAPM Practice Test practice questions, page 12 of 21, with answer review and explanations.
Question 56
A project manager is working on the communications management plan. Which of these documents are inputs to consider?
Stakeholder engagement plan and organizational process assets
Project schedule and stakeholder register
Quality management plan and risk register
Basis of estimates and scope baseline
Question 57
According to the PMI Talent Triangle, leadership skills relate to the ability to:
understand the high-level overview of the organization
tailor traditional and agile tools for the project
work with stakeholders to develop an appropriate project delivery
guide, motivate, and direct a team to reach project goals
Question 58
Which is the best way for a project manager to ensure efficient and frequent communication with management and stakeholders in an agile/adaptive environment?
Post project artifacts in a transparent fashion and engage stakeholders on a regular basis.
Make surveys among the stakeholders and meet with the team once a month.
Create a social network and post news there.
Create personalized emails for each stakeholder, asking for requests and reviewing objectives with them periodically.
Question 59
A project manager is assigned to a strategic project. Senior management asks the project manager to give a presentation in order to request support that will ensure the success of the project. Which entities will the project manager attempt to influence?
The project and the organization
The organization and the industry
The subject matter experts and the project
The change control board and the organization
Question 60
Which statement summarizes the role of the change control board?
The change control board is responsible for presenting the change for approval
The change control board will analyze the change impact in terms of cost and schedule
The change control board is responsible for managing the change management and configuration management systems
The change control board is responsible for reviewing and approving changes to the project