Question 40
In a preliminary meeting for a project, team members decide to execute the project with agile methodology. A finance team member wants to know how project cost will be determined at this early stage. How will the project team determine project cost?
Use a lightweight cost estimation due to the nature of agile projects
Use a detailed cost estimation for agile projects
Retrieve a budget from a previous project and create a baseline for this project based on it
Use a detailed work breakdown structure (WBS) to get cost estimation