Question 31

Why is tailoring required in a project?

  1. Because a one-size-fits-all approach avoids complications and saves time
  2. Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required
  3. Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project
  4. Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required

Question 32

Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?

  1. Internal enterprise environmental factor
  2. Risk register database
  3. External enterprise environmental factor
  4. Organizational process asset

Question 33

Which of the following documents are created as part of Project Integration Management?

  1. Project charter and project management plan
  2. Communications management plan and scope management plan
  3. Quality management plan and risk management plan
  4. Project scope statement and communications management plan

Question 34

A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?

  1. Three-point estimating
  2. Parametric estimating
  3. Bottom-up estimating
  4. Data analysis

Question 35

A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI's Talent Triangle best relates to this need to improve?

  1. Strategic and business management skills
  2. Leadership skills
  3. Technical project management
  4. Organizational management