CAPM Practice Test practice questions, page 7 of 21, with answer review and explanations.
Question 31
Why is tailoring required in a project?
Because a one-size-fits-all approach avoids complications and saves time
Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required
Because tailoring allows us to identify the techniques, procedures, and system practices used by those in the project
Project managers should apply every process in the PMBOK Guide to the project, so tailoring is not required
Question 32
Company A has just been notified about a new legal requirement for its business operations. What is the classification of this item?
Internal enterprise environmental factor
Risk register database
External enterprise environmental factor
Organizational process asset
Question 33
Which of the following documents are created as part of Project Integration Management?
Project charter and project management plan
Communications management plan and scope management plan
Quality management plan and risk management plan
Project scope statement and communications management plan
Question 34
A project manager is working on an estimate. The project team is estimating each work package and then finding the total of all the work packages. Which technique is the project manager using?
Three-point estimating
Parametric estimating
Bottom-up estimating
Data analysis
Question 35
A project manager is updating their CV or resume and realizes that they need to improve skills related to expertise in the industry and organizational knowledge. Which dimension of PMI's Talent Triangle best relates to this need to improve?