Question 16
Given the following information: ✑ Activity A takes one week. ✑ Activity B takes three weeks. ✑ Activity C takes two weeks. ✑ Activity D takes five weeks. ✑ Activity A starts at the same time as Activity B. ✑ Activity C follows Activity B and Activity A. ✑ Activity D follows Activity C. How long will it take to complete the project?
8 weeks
9 weeks
10 weeks
11 weeks
Question 17
Which is an example of analogous estimating?
Estimates are created by individuals or groups with specialized knowledge.
Estimates are created by using information about resources of previous similar projects.
Estimates are created by analyzing data.
Estimates are created at the task level and aggregated upwards.
Question 18
With regard to a project manager's sphere of influence in a project, which of the following does the project manager influence most directly?
Suppliers
Customers
Governing bodies
Project team
Question 19
Which document can help a project manager to leverage historical project information?
Lessons learned register
Schedule baseline
Work performance data
Deliverable acceptance forms
Question 20
Which kind of communication should the project manager use when creating reports for government bodies?