CAPM Practice Test

CAPM Practice Test practice questions, page 3 of 21, with answer review and explanations.

Question 11

In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with charges?

  1. Having control over the planning and delivery of the products without delegating decisions
  2. Giving access to information to the team and frequent team checkpoints
  3. Selecting different team members to take the project manager role during reviews with stakeholders
  4. Asking the control change board to approve changes before notifying the team

Question 12

The activity of tailoring is necessary because:

  1. the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide; this is required for all projects.
  2. each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.
  3. the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects.
  4. each project is unique, and the project team must plan how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide.

Question 13

When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process:

  1. Develop Schedule
  2. Define Activities
  3. Define Scope
  4. Collect Requirements

Question 14

Which of the following tasks focuses on decomposing work packages?

  1. Adjust duration estimates
  2. Define activities
  3. Complete rolling wave planning
  4. Develop milestone list

Question 15

During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?

  1. Initiating
  2. Planning
  3. Executing
  4. Monitoring and Controlling