Question 11
In an adaptive project environment, which action helps the project manager ensure that the team is comfortable with charges?
Having control over the planning and delivery of the products without delegating decisions
Giving access to information to the team and frequent team checkpoints
Selecting different team members to take the project manager role during reviews with stakeholders
Asking the control change board to approve changes before notifying the team
Question 12
The activity of tailoring is necessary because:
the members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide; this is required for all projects.
each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.
the members of the project team need to understand the PMBOK Guide processes, which are applied to all projects.
each project is unique, and the project team must plan how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide.
Question 13
When developing the project schedule, a project manager uses decomposition and rolling wave planning techniques in this process:
Develop Schedule
Define Activities
Define Scope
Collect Requirements
Question 14
Which of the following tasks focuses on decomposing work packages?
Adjust duration estimates
Define activities
Complete rolling wave planning
Develop milestone list
Question 15
During what project management process does the project manager invest the most effort into creating the work breakdown structure (WBS)?