CAPM Practice Test practice questions, page 2 of 21, with answer review and explanations.
Question 6
A project is in progress and about to move to a different phase, according to the plan. This will be a good opportunity for the project manager to:
create the project management plan.
identify the project objectives.
review and update stakeholder engagement.
create the schedule baseline.
Question 7
A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?
8
18
36
40
Question 8
A project manager is preparing to meet with three crucial project stakeholders on a new project. Which tools and techniques can the project manager use to capture stakeholder interest?
Review stakeholder register and meeting
Data analysis and communication skills
Data gathering and data analysis
Communication skills and cultural awareness
Question 9
Select three processes that are associated with Project Schedule Management? (Choose three.)
Define Activities
Plan Resource Management
Estimate Activity Durations
Develop Schedule
Acquire Resources
Question 10
What are the project management processes associated with project quality management?
Plan Quality Management, Manage Quality, and Control Quality
Plan Quality Management, Manage Quality, and Cost of Quality
Manage Quality, Customer Satisfaction, and Control Quality
Customer Satisfaction, Control Quality, and Continuous Improvement