Question 26

When alternative dispute resolution (ADR) is necessary, which tool or technique should be utilized?

  1. Interactive communication
  2. Claims administration
  3. Conflict management
  4. Performance reporting

Question 27

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

  1. Interrelationship digraphs
  2. Tree diagram
  3. Affinity diagram
  4. Network diagram

Question 28

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

  1. Planning.
  2. Executing,
  3. Monitoring and Controlling.
  4. Closing.

Question 29

Organizational theory is a tool used in which Project Human Resource Management process?

  1. Manage Project Team
  2. Acquire Project Team
  3. Develop Project Team
  4. Plan Human Resource Management

Question 30

Which tools or techniques are used in the Plan Schedule Management process?

  1. Benchmarking, expert judgment, and analytical techniques
  2. Statistical sampling, benchmarking, and meetings
  3. Negotiations, pre-assignment, and multi-criteria decision analysis
  4. Expert judgment, analytical techniques, and meetings