Question 1

Which document defines how a project is executed, monitored and controlled, and closed?

  1. Strategic plan
  2. Project charter
  3. Project management plan
  4. Service level agreement

Question 2

Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?

  1. Risk and uncertainty increase; the cost of changes increases.
  2. Risk and uncertainty increase; the cost of changes decreases,
  3. Risk and uncertainty decrease; the cost of changes increases.
  4. Risk and uncertainty decrease; the cost of changes decreases.

Question 3

Which tool or technique is used in the Plan Scope Management process?

  1. Document analysis
  2. Observations
  3. Product analysis
  4. Expert judgment

Question 4

Which tool or technique is an examination of industry and specific vendor capabilities?

  1. Independent estimates
  2. Market research
  3. Analytical techniques
  4. Bidder conferences

Question 5

An input used in developing the communications management plan is:

  1. Communication models.
  2. Enterprise environmental factors.
  3. Organizational communications,
  4. Organizational cultures and styles.