Question 1
Which document defines how a project is executed, monitored and controlled, and closed?
- Strategic plan
- Project charter
- Project management plan
- Service level agreement
Question 2
Which changes occur in risk and uncertainty as well as the cost of changes as the life cycle of a typical project progresses?
- Risk and uncertainty increase; the cost of changes increases.
- Risk and uncertainty increase; the cost of changes decreases,
- Risk and uncertainty decrease; the cost of changes increases.
- Risk and uncertainty decrease; the cost of changes decreases.
Question 3
Which tool or technique is used in the Plan Scope Management process?
- Document analysis
- Observations
- Product analysis
- Expert judgment
Question 4
Which tool or technique is an examination of industry and specific vendor capabilities?
- Independent estimates
- Market research
- Analytical techniques
- Bidder conferences
Question 5
An input used in developing the communications management plan is:
- Communication models.
- Enterprise environmental factors.
- Organizational communications,
- Organizational cultures and styles.