Question 6

Regression analysis, failure mode and effect analysis (FMEA), fault tree analysis (FTA), and trend analysis are examples of which tool or technique?

  1. Expert judgment
  2. Forecasting methods
  3. Earned value management
  4. Analytical techniques

Question 7

The Perform Quality Assurance process occurs in which Process Group?

  1. Executing
  2. Monitoring and Controlling
  3. Initiating
  4. Planning

Question 8

Enterprise environmental factors are an input to which process?

  1. Control Scope
  2. Define Scope
  3. Plan Scope Management
  4. Collect Requirements

Question 9

Which process develops options and actions to enhance opportunities and reduce threats to project objectives?

  1. Identify Risks
  2. Control Risks
  3. Plan Risk Management
  4. Plan Risk Responses

Question 10

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

  1. Plan Schedule Management.
  2. Develop Project Charter.
  3. Develop Schedule.
  4. Plan Scope Management.