Question 11

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

  1. Issue log
  2. Change log
  3. Expert judgment
  4. Change requests

Question 12

An input to the Plan Stakeholder Management process is:

  1. The project charter.
  2. The stakeholder analysis.
  3. A communication management plan.
  4. A stakeholder register.

Question 13

An input to the Plan Cost Management process is:

  1. Cost estimates.
  2. Resource calendars,
  3. The project charter,
  4. The risk register.

Question 14

A technique used to determine the cause and degree of difference between baseline and actual performance is:

  1. Product analysis.
  2. Variance analysis.
  3. Document analysis,
  4. Decomposition.

Question 15

The process of identifying and documenting project roles, responsibilities, required skills, and reporting relationships and creating a staffing management plan is known as:

  1. Develop Project Team.
  2. Manage Project Team.
  3. Acquire Project Team.
  4. Plan Human Resource Management.