Question 16
Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?
Mandatory
Discretionary
Internal
External
Question 17
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
Monitor and Control Project Work
Perform Quality Assurance
Close Project or Phase
Control Scope
Question 18
An input to the Manage Project Team process is:
Work performance reports.
Change requests.
Activity resource requirements.
Enterprise environmental factors.
Question 19
Which input provides suppliers with a clear set of goals, requirements, and outcomes?
Procurement statement of work
Purchase order
Source selection criteria
Bidder conference
Question 20
A large portion of a projects budget is typically expended on the processes in which Process Group?