Question 16

Which type of dependency is legally or contractually required or inherent in the nature of work and often involves physical limitations?

  1. Mandatory
  2. Discretionary
  3. Internal
  4. External

Question 17

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

  1. Monitor and Control Project Work
  2. Perform Quality Assurance
  3. Close Project or Phase
  4. Control Scope

Question 18

An input to the Manage Project Team process is:

  1. Work performance reports.
  2. Change requests.
  3. Activity resource requirements.
  4. Enterprise environmental factors.

Question 19

Which input provides suppliers with a clear set of goals, requirements, and outcomes?

  1. Procurement statement of work
  2. Purchase order
  3. Source selection criteria
  4. Bidder conference

Question 20

A large portion of a projects budget is typically expended on the processes in which Process Group?

  1. Executing
  2. Planning
  3. Monitoring and Controlling
  4. Closing