Question 21
A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?
- Efficient
- Effective
- Push
- Pull
Question 22
Scope, schedule, and cost parameters are integrated in the:
- Performance measurement baseline.
- Analysis of project forecasts,
- Summary of changes approved in a period,
- Analysis of past performance.
Question 23
A project in which the scope, time, and cost of delivery are determined as early as possible is following a life cycle that is:
- Adaptive
- Predictive
- Incremental
- Iterative
Question 24
What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?
- 0.50
- 0.67
- 1.50
- 2.00
Question 25
Which item is an input to the Define Activities process?
- Schedule data
- Activity list
- Risk register
- Scope baseline