Question 31
A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?
Projectized
Weak matrix
Functional
Balanced matrix
Question 32
A project charter is an output of which Process Group?
Executing
Planning
Initiating
Closing
Question 33
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Inspection
Variance analysis
Decomposition
Product analysis
Question 34
An element of the project scope statement is:
Acceptance criteria.
A stakeholder list.
A summary budget.
High-level risks.
Question 35
Which document describes the necessary information to determine if a project is worth the required investment?