Question 31

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

  1. Projectized
  2. Weak matrix
  3. Functional
  4. Balanced matrix

Question 32

A project charter is an output of which Process Group?

  1. Executing
  2. Planning
  3. Initiating
  4. Closing

Question 33

Which tool or technique is effective in a project in which the deliverable is not a service or result?

  1. Inspection
  2. Variance analysis
  3. Decomposition
  4. Product analysis

Question 34

An element of the project scope statement is:

  1. Acceptance criteria.
  2. A stakeholder list.
  3. A summary budget.
  4. High-level risks.

Question 35

Which document describes the necessary information to determine if a project is worth the required investment?

  1. Cost baseline
  2. Service level agreement
  3. Memorandum of understanding
  4. Business case