Question 126

An input to Close Project or Phase is:

  1. Accepted deliverables,
  2. Final products or services,
  3. Document updates,
  4. Work performance information.

Question 127

An output of the Direct and Manage Project Work process is:

  1. Deliverables.
  2. Activity lists.
  3. A work breakdown structure.
  4. A scope statement.

Question 128

External organizations that have a special relationship with the enterprise and provide specialized expertise are called:

  1. Customers.
  2. Business partners.
  3. Sellers.
  4. Functional managers.

Question 129

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

  1. Develop Schedule
  2. Create VVBS
  3. Estimate Activity Resources
  4. Define Scope

Question 130

In a project, total float measures the:

  1. Ability to shuffle schedule activities to lessen the duration of the project.
  2. Amount of time an activity can be extended or delayed without altering the project finish date.
  3. Cost expended to restore order to the project schedule after crashing the schedule.
  4. Estimate of the total resources needed for the project after performing a forward pass.