Question 121
Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
Organizational process updates
Quality metrics
Change requests
Quality control measurements
Question 122
A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?
Urgent information need
Sensitivity of information
Project environment
Ease of use
Question 123
The number of potential communication channels for a project with 5 stakeholders is:
10.
12.
20.
24.
Question 124
The process of prioritizing risks for further analysis or action is known as:
Plan Risk Management.
Plan Risk Responses.
Perform Qualitative Risk Analysis.
Perform Quantitative Risk Analysis.
Question 125
Which tool or technique is used in validating the scope of a project?