Question 121

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

  1. Organizational process updates
  2. Quality metrics
  3. Change requests
  4. Quality control measurements

Question 122

A project manager managing a cross-cultural virtual project team across several time zones should be concerned about the impacts of which communication technology factor?

  1. Urgent information need
  2. Sensitivity of information
  3. Project environment
  4. Ease of use

Question 123

The number of potential communication channels for a project with 5 stakeholders is:

  1. 10.
  2. 12.
  3. 20.
  4. 24.

Question 124

The process of prioritizing risks for further analysis or action is known as:

  1. Plan Risk Management.
  2. Plan Risk Responses.
  3. Perform Qualitative Risk Analysis.
  4. Perform Quantitative Risk Analysis.

Question 125

Which tool or technique is used in validating the scope of a project?

  1. Facilitated workshops
  2. Interviews
  3. Inspection
  4. Meetings