Question 116

Which grid shows which resources are tied to work packages?

  1. Work breakdown structure (WBS)
  2. Responsibility assignment matrix (RAM)
  3. Project assignment chart
  4. Personnel assignment matrix

Question 117

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

  1. Continuous improvement.
  2. Predictive planning.
  3. Progressive elaboration.
  4. Quality assurance.

Question 118

An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:

  1. smooth/accommodate.
  2. force/direct,
  3. collaborate/problem solve,
  4. compromise/reconcile.

Question 119

A temporary endeavor that creates a unique product or service is called a:

  1. Project
  2. Plan
  3. Program
  4. Portfolio

Question 120

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

  1. Earned value management.
  2. Enterprise environmental factors.
  3. Organizational process assets.
  4. Work performance information.