Question 111

The Monitoring and Controlling Process Group includes processes that:

  1. Establish the scope, objectives, and course of action of a project,
  2. Define a new project or a new phase of an existing project.
  3. Track, review, and regulate the progress and performance of a project.
  4. Complete the work defined in the project management plan.

Question 112

Which Control Quality tool is also known as an arrow diagram?

  1. Matrix diagram
  2. Affinity diagram
  3. Tree diagram
  4. Activity network diagram

Question 113

A project manager builds consensus and overcomes obstacles by employing which communication technique?

  1. Listening
  2. Facilitation
  3. Meeting management
  4. Presentation

Question 114

When does the project team determine which dependencies are discretionary?

  1. Before the Define Activities process
  2. During the Define Activities process
  3. Before the Sequence Activities process
  4. During the Sequence Activities process

Question 115

Typical outcomes of a project include:

  1. Products, services, and improvements.
  2. Products, programs, and services.
  3. Improvements, portfolios, and services.
  4. Improvements, processes, and products.