Question 111
The Monitoring and Controlling Process Group includes processes that:
- Establish the scope, objectives, and course of action of a project,
- Define a new project or a new phase of an existing project.
- Track, review, and regulate the progress and performance of a project.
- Complete the work defined in the project management plan.
Question 112
Which Control Quality tool is also known as an arrow diagram?
- Matrix diagram
- Affinity diagram
- Tree diagram
- Activity network diagram
Question 113
A project manager builds consensus and overcomes obstacles by employing which communication technique?
- Listening
- Facilitation
- Meeting management
- Presentation
Question 114
When does the project team determine which dependencies are discretionary?
- Before the Define Activities process
- During the Define Activities process
- Before the Sequence Activities process
- During the Sequence Activities process
Question 115
Typical outcomes of a project include:
- Products, services, and improvements.
- Products, programs, and services.
- Improvements, portfolios, and services.
- Improvements, processes, and products.