APM-001 practice questions, page 22 of 28, with answer review and explanations.
Question 106
The basis of identification for current or potential problems to support later claims or new procurements is provided by:
A risk urgency assessment.
The scope baseline.
Work performance information.
Procurement audits.
Question 107
Which Collect Requirements output links the product requirements to the deliverables that satisfy them?
Requirements documentation
Requirements traceability matrix
Project management plan updates
Project documents updates
Question 108
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Cost management plan.
Work performance information.
Quality management plan.
Work breakdown structure.
Question 109
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
External
Internal
Mandatory
Discretionary
Question 110
Sensitivity analysis is typically displayed as a/an: