APM-001

APM-001 practice questions, page 22 of 28, with answer review and explanations.

Question 106

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

  1. A risk urgency assessment.
  2. The scope baseline.
  3. Work performance information.
  4. Procurement audits.

Question 107

Which Collect Requirements output links the product requirements to the deliverables that satisfy them?

  1. Requirements documentation
  2. Requirements traceability matrix
  3. Project management plan updates
  4. Project documents updates

Question 108

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

  1. Cost management plan.
  2. Work performance information.
  3. Quality management plan.
  4. Work breakdown structure.

Question 109

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?

  1. External
  2. Internal
  3. Mandatory
  4. Discretionary

Question 110

Sensitivity analysis is typically displayed as a/an:

  1. Decision tree diagram.
  2. Tornado diagram.
  3. Pareto diagram.
  4. Ishikawa diagram.